large-map

Cedar Creek Remediation

Dec. 14, 2012, noon

Project Update 3

Week of December 9th - 15th, 2012

At this stage of the project, all concrete and soil removal/disposal activities are complete.  We are currently completing the placement of the clay cover, which will be finished by the end of the week  With the unseasonable weather, we intend to get the ...

Read more

Nov. 12, 2012, 4 p.m.

Project Update 2

Week of Nov. 4th through Nov. 10th

Progress this week included removal of 2' of impacted soil along the western perimeter of the former Plant 2 building. Also, the placement of clean fill material along the western perimeter following the removal of impacted soils.

Read more

Nov. 5, 2012, 11:24 a.m.

Project Update 1

Week of Oct. 29th through Nov. 2nd

The construction team was busy preparing the work site for the field office and water equipment. In addition, the staging areas for soil removal and site containment for surface water control were prepared. Next week will include soil removal around the perimeter of ...

Read more

Oct. 19, 2012, 1:17 p.m.

Work Plan for Mercury Marine Property in Cedarburg

Mercury Marine will perform these activities at its property in Cedarburg in the coming months. This work will include the removal of PCB-impacted materials (e.g., soil, concrete slab) from the site and placement of a soil/grass (low-permeability) cap. Work at the site will be performed from 7 a ...

Read more