Dec. 14, 2012, noon
Project Update 3
Week of December 9th - 15th, 2012
At this stage of the project, all concrete and soil removal/disposal activities are complete. We are currently completing the placement of the clay cover, which will be finished by the end of the week With the unseasonable weather, we intend to get the ...
Read moreNov. 12, 2012, 4 p.m.
Project Update 2
Week of Nov. 4th through Nov. 10th
Progress this week included removal of 2' of impacted soil along the western perimeter of the former Plant 2 building. Also, the placement of clean fill material along the western perimeter following the removal of impacted soils.
Read moreNov. 5, 2012, 11:24 a.m.
Project Update 1
Week of Oct. 29th through Nov. 2nd
The construction team was busy preparing the work site for the field office and water equipment. In addition, the staging areas for soil removal and site containment for surface water control were prepared. Next week will include soil removal around the perimeter of ...
Read moreOct. 19, 2012, 1:17 p.m.
Work Plan for Mercury Marine Property in Cedarburg
Mercury Marine will perform these activities at its property in Cedarburg in the coming months. This work will include the removal of PCB-impacted materials (e.g., soil, concrete slab) from the site and placement of a soil/grass (low-permeability) cap. Work at the site will be performed from 7 a ...
Read more